Decision log

Run 1 final GDS

  • Changed guidance — 2025-12-03: Foundry rule changes made the final GDS deadline TBD, though initial GDS was still due. (archive message; Discord)
  • Final decision — 2025-12-10: DRC-clean GDS was due 2025-12-17 at 23:59 AoE. (archive message; Discord)

Run 2 schedule

  • Obsolete proposal — 2025-11-07: Tim Ansell expected Run 1 back in March 2026 and asked whether Run 2 should close only after users had working silicon. This was planning, not a commitment. (archive message; Discord)
  • Obsolete estimate — 2026-01-23: June looked likely, but the Run 2 date was still TBD. (archive message; Discord)
  • Obsolete planning aid — 2026-02-10: A schedule spreadsheet was supplied with a warning that dates would change until GF confirmed wafer-out. (archive message; Discord)
  • Final decision — 2026-07-10: GDS was due 2026-07-15 at 11:59, with the stated platform gates. (archive message; Discord)

Run 3 dates

  • Obsolete estimate — 2026-07-17: Run 3 would likely open August 1 with a mid-December submission date. (archive message; Discord)
  • Final archive decision — 2026-08-03: The pinned launch set early-bird end to 2026-09-30, purchase close to 2026-12-09, and GDS due date to 2026-12-16. (archive message; Discord)
  • Proposal, not schedule: Tim Ansell said quarterly runs in 2027 were likely if Run 3 succeeded. (archive message; Discord)

Submission transport and revisions

  • Obsolete guidance — 2025-11-19: Community messages used a test-platform GDS URL plus MD5 or SHA1. (archive message; Discord)
  • Later confirmed procedure — 2026-07-10: The official Run 2 path used project upload, current precheck, order association, CoB selection when applicable, and submitted for manufacturing. (archive message; Discord)
  • Confirmed platform behavior — 2026-07-10: A new manufacturing revision could be selected until the deadline. (archive message; Discord)
  • Run-specific stop — 2026-07-15: After the Run 2 deadline, users were told to stop layout changes. (archive message; Discord)

Tool versions

  • Archive checkpoint — 2026-07-14: Project Template 1.5.8 and Precheck 1.7.2 were the last explicit pair announced in the archive. This is not a promise that they remain current. (archive message; Discord)

Sources

  • 1445784146331959390 — 2025-12-03T14:30:01.856+00:00 — Tim 'mithro' Ansell — archiveDiscord — Run 1 provisional deadline and foundry changes.
  • 1448290154966945936 — 2025-12-10T12:28:00.874+00:00 — Tim 'mithro' Ansell — archiveDiscord — Run 1 final deadline.
  • 1436214302230188226 — 2025-11-07T04:42:53.223+00:00 — Tim 'mithro' Ansell — archiveDiscord — Early Run 2 planning proposal.
  • 1464397089118093559 — 2026-01-23T23:11:13.228+00:00 — Tim 'mithro' Ansell — archiveDiscord — June estimate marked TBD.
  • 1470659897476644864 — 2026-02-10T05:57:23.098+00:00 — Tim 'mithro' Ansell — archiveDiscord — Provisional schedule spreadsheet.
  • 1524956674861957282 — 2026-07-10T01:53:23.612+00:00 — Tim 'mithro' Ansell — archiveDiscord — Final Run 2 deadline and submission path.
  • 1527505603616833596 — 2026-07-17T02:41:55.584+00:00 — Tim 'mithro' Ansell — archiveDiscord — Run 3 estimate and conditional quarterly-run proposal.
  • 1533765674281730048 — 2026-08-03T09:17:12.737+00:00 — Andrew Wingate — archiveDiscord — Pinned Run 3 launch dates.
  • 1440824970979573812 — 2025-11-19T22:04:02.315+00:00 — urish — archiveDiscord — Earlier test-platform transport.
  • 1525184072932917288 — 2026-07-10T16:56:59.537+00:00 — Leo Moser — archiveDiscord — Revision selection until deadline.
  • 1526924792563761303 — 2026-07-15T12:13:59.438+00:00 — Leo Moser — archiveDiscord — Run 2 post-deadline stop instruction.
  • 1526579676183662662 — 2026-07-14T13:22:37.281+00:00 — Leo Moser — archiveDiscord — Latest explicit tool pair in archive.